Building Vanguard: The 2023–24 Build Timeline

Between July 2023 and March 2024 we wrote eighteen weekly updates from the yard in Antalya. Read in order, they tell one story: a hull full of tradesmen becoming a yacht that moves, then a yacht that moves badly, then one that moves properly. This is that story in one place, with the dates, the numbers and the mistakes.
The mistakes are the useful part. Everything below happened on a new design, in a yard that had to learn a few things at our expense and we at theirs.
Summer 2023: wires, welds and one stubborn solar panel
15 July 2023 Twenty to twenty-five tradesmen in four teams were on board. About 15 km of cable was run and roughly 80% of it was installed. The house batteries moved to the engine room, with charging limited to 24 V and 80 A to satisfy MGN 280. Navantec began fitting the driveline: John Deere engines, Esco hybrid drive, Twin Disc gearbox and a Bruntons CV joint.
29 July The skegs were welded, three layers of 12 mm plate plus a 24 mm rubbing strake. The Intersleek 1100 antifouling arrived, the instrument mast went on, and the tender's engine and jet drive were fitted at Hebbeke in the Netherlands.
5 August The solar panels would not stay stuck. The fix, from Akan and Engin, was Sikaflex and the right primers, which became known as the Chicken Little episode. The sky did not fall; the panels stayed on. Epoxy filled the gaps between the stern tubes and the rudder blades were pressure tested.
11 August Antifouling went on (Intersleek 1100SR) with the waterline set for the fully loaded condition, 7.5 tonnes of water and 9.9 tonnes of diesel. A hull protector plate was added for the 110 kg Rocna anchor, and a bulkhead was cut out to fit the washing machine.
25 August The tender passed its Factory Acceptance Test at Hebbeke in Hoorn.
Autumn 2023: launch, and an argument between two stability programs
9 September 750 mm Bruntons auto-props were fitted, the rudders went on, the shaft lines were in and the helm station was going in. Glazing is three 8 mm sheets of toughened glass, 26 mm overall.
23 September A night-vision camera was installed. The helm was 85% complete with the Praxis DP system. 350 ft of 13 mm G40 anchor chain was marked, and Starlink and the Furuno satcom moved forward.
3 October Vanguard was launched. She floated with a list of about 50 mm to port and a roll period of roughly 7.5 seconds, and was then ballasted with fresh water.
4 November Longitudinal stability took the week. Orca3D and Maxsurf disagreed, so we ran an inclining test and took advice from Eyos and Artnautica.
10 November The Victron electrical system was reviewed: four solar controllers fed by 6 kW of panels arranged to a 96 VDC maximum, Skylla-i isolation for shore power, and three MultiPlus inverters at 5 kVA each, giving a maximum load of 12 kW. The hotel system can draw on 120 kWh of propulsion batteries as well as 21 kWh of house batteries.
18 November At the METS show in Amsterdam we learned the MultiPlus units treat "grid" as the main source and solar as the backup, which is not much use when the grid is a set of big batteries. Victron's Preferential Solar setting fixed it. The same trip took us to DMS in the Netherlands to see the Magnusmaster stabilizers.
Winter 2023: commissioning, and a quiet Christmas at the dock
9 December Praxis Automation began bringing the hybrid drives and DC battery to life. Five MFD displays came up, three phase shore power was live, and the two John Deere 4045 engines started on their local controls. The emergency Wills Ridley steering was connected, the tender arrived from the Netherlands and 3,000 L of diesel, about 30% of capacity, was ordered for sea trials.
30 December Both engines ran after Praxis decoded the J1939 CAN signals (their first John Deere installation). Three steering systems worked: emergency manual, Praxis and Wills Ridley. BEP ultrasonic tank gauges reported to the MIMIC displays. 3,000 kg of lead ballast was on order, the MCA surveyor was booked for the Category 0 survey, and the CE survey had passed.
January to February 2024: sea trials, and what they found
5 January The first three-hour sea trial: calm, light wind, no permanent ballast, stabilizers folded. At 1,000 rpm she made 6.7 knots on hybrid drive, at 1,500 rpm 9.8 knots, and at 1,680 rpm 11.3 knots. That beat our estimated cruising speed by 1.3 knots at about 60% of installed power. The bow wave was close to non-existent.
20 January Insurance proved harder than the engineering. A good Pantaenius quote disappeared when they stopped underwriting anything connected with the USA. We found a workable policy through Garrison Rudisill at Maritime Insurance International, covering the Mediterranean and the North Atlantic. The yard also needed a refit policy to carry on with trials. Webasto HVAC and hot water were working.
10 February The steering was commissioned after launch. The faults were a reversed hydraulic pipe on the starboard rudder and a gateway with its power supply connected the wrong way round. The rudders were recalibrated to a full 35 degrees each way. A vibration above roughly 1,900 rpm was still unexplained.
24 February The vibration turned out to be two problems. At idle, the 600 rpm setting sat on a harmonic and went away at 700 to 750 rpm, the book value. Under load the vibration began at about 1,800 rpm. We hauled out and found scored rope cutters, rubbing wear against the anode, and shafts that had crept forward on their couplings. The cutter restraining bracket had been installed hard against its disc, so ahead thrust loaded the fixed blade and made it strike the rotating blade. The manual warned against exactly that. We also suspect the couplings were never torqued correctly after the first run. New cutters and a "tell" mark on the shaft were the answer, with a load test at the dock before the next trial.
March 2024: the plumber we did not keep
30 March Back from the US, we inspected what the yard had finished. The coolant plumbing for the high-voltage hybrid accessories was the worst of it: pipes tied to data cables, pressurised joints within 12 inches of 600 VDC batteries, taper threads in parallel sockets, shortened spigots and mixed metals. After two days of correcting small faults we pulled it all out and re-fitted it under our own supervision. The same week the CE certificate (Category A) was issued by the Dutch Certification Institute, after an inclining test supervised by a UK MCA surveyor to ISO 12217.
What we took from it
Three lessons, none of them new, all of them paid for. Read the installation manual before the work, not after the vibration. A system that works is not the same as one that is seaworthy. And a supplier director who attends commissioning in person is worth more than any brochure promise.
We were aiming to leave Antalya at the end of April 2024. Since then Vanguard has crossed to Greenland and back. The long way round is the only way we know to find the problems in a yacht.